Production Steps of Square-Type Vacuum Drying Equipment

176 views

 Steps of  Square-Type Vacuum Drying / Vacuum Tray Dryer Equipment

The production of square-type vacuum drying equipment starts from design and material cutting, and proceeds through welding, machining, assembly, pressure testing, and trial operation. The following are the 12 steps:

  1. Design drawing and material procurement: Complete the structural design according to capacity, temperature, and vacuum degree requirements, draw drawings, and procure stainless steel plates, heating elements, and sealing parts.
  2. Plate cutting and bending forming: Stainless steel plates are cut on a shearing machine and formed on a bending machine; the inner liner and outer shell are processed separately, with dimensional accuracy controlled to the millimeter level.
  3. Full welding of inner cylinder and corner treatment: The inner cylinder is fully welded to ensure sealing; R50 stainless steel corner pieces are fully welded at right angles, with smooth transitions at seams to eliminate cleaning dead corners.
  4. Polishing of inner surface to low roughness: The inner cylinder and corner welds are ground and polished section by section, achieving a roughness of Ra ≤ 0.4 μm to prevent material adhesion and residue.
  5. Insulation filling and outer cover plate welding: Aluminum silicate fiber cotton is filled between the inner liner and outer shell, and the outer cover plate is welded to enclose the insulation layer, reducing equipment heat loss.
  6. Bracket fabrication and layered pressure testing: Stainless steel tubes are cut and drilled, then mirror-polished; they are assembled and welded layer by layer and acid-pickled; the whole assembly is hydrostatically tested at 1.0–1.2 MPa and held for 2 hours.
  7. Finishing of door body and sealing parts: The door flange is planed and then a mushroom-shaped seal groove is machined; the door frame and chamber body are welded together and then planed as a whole to ensure tight sealing of the door body.
  8. Integration of piping and vacuum interfaces: Seamless steel pipes are used for connecting pipes; the vacuum cover is rolled and welded after opening with a 50% open area; T-shaped female threaded connectors are provided at interfaces for easy disassembly and cleaning.
  9. Electrical control cabinet assembly and wiring: Install PLC, temperature control modules, vacuum gauges, and touch screens; complete electrical wiring; and write logic programs for temperature control and vacuum pumping.
  10. Chamber air-tightness and tube bundle hydrostatic tests: The chamber is subjected to an air-tightness test at 0.196 MPa gauge pressure, and the heating tube bundle is subjected to a hydrostatic test at 1.0 MPa, held for 30 minutes with no leakage.
  11. No-load trial operation and vacuum retention inspection: Start the vacuum pump and heating system for no-load operation, and record the baseline of ultimate vacuum degree, temperature uniformity, and pressure rise rate.
  12. Surface treatment and finished product packaging and warehousing: The outer surface is brushed or powder-coated, cleaned, and covered with protective film; it is packed in wooden cases with pressure test and trial operation records attached.

 

   Steps of  Square-Type Vacuum Drying / Vacuum Tray Dryer Equipment

 

 

YANCHENG QUANPIN MACHINERY CO.. LTD
Sales Manager - Stacie Tang
MP: +86 19850785582
Tel: +86 0515-69038899
E-mail: stacie@quanpinmachine.com
WhatsAPP: 8615921493205

https://www.quanpinmachine.com/

https://quanpindrying.en.alibaba.com/

Address: Jiangsu Province, China.


Post time: Nov-09-2026